Construction Steps

sun.gif

Interested in knowing what the steps are in building a new pool? 
Below is the proper construction sequence that Coral Pool follows. Prior to excavation we would make an appointment with Sunshine, to check for underground utilities.
  
1. Swimming pool layout. (Marking the pool)
2. Pool excavation
3. Pool forming
4.Steel and main drain installation
5. Inspection of steel and main drain. (In some cities also nich inspection) 
6. Application of Shotcrete
7.First backfill, after removal of forming
8. Installation of plumbing
9. Inspection of plumbing
10. Installation of tile and coping
11. Installation of lights, grounding and electrical equipment
12. 2nd. backfill
13.Electrical rough inspection of lights, grounding and electrical equipment
14. Preparation for paver and installation
15. Installation of pump, filter, etc.
16. Electrical hookup
17. Application of pool finish 
18. Fill pool with water
19. Start up, chemically balance water
20. Give instructions on operation of equipment
21. Final inspections of electrical, plumbing and building. (Some cities require setback and zoning inspection.) 
____________________________________________________________
After the initial startup, the customer is responsible for maintaining the pool. We recommend that you hire a pool cleaning service for at least the first 2 or 3 months, while you become familiar with how to best care for and maintain your new pool.
_____________________________________________________________

Pool Forming

Concrete

Swimming Pool

Lic & Ins. CPC013095

Swimming Pool Magazine.com pool design, building and contracting questions are answered.

Home
About Us
Here are some of the latest swimming pools built by Coral Pool!
Contact Information
Construction Steps
The Coral Pool Package
Product Samples
Pool Designs
Links